Musha Substation
Construction of a new 110/15 kV Substation starting to the plot arrangement up to commissioning including
installation of two 110kV End Towers to reroute the
Line and stringing the incoming and outgoing spans
Client: EUCL
Location: Kigali, Musha
Services: Substation Rehabilitation
Period:From October 2012 up to March 2014
Sustainable, Reliable & Affordable Energy!
Providing Value To Our ClientsThrough Ongoing Product & Innovation.
While improving the yield and performance of solar energy products, our PV industry experience enables us to provide in-depth material sourcing, financing and supply chain expertise for every step.
Raw polycrystalline silicon for PV manufacturing. Offered in various grades and formats including chunks, chips, powder and ingot.
110 kV Transmission line Gahanga-Rilima to New Bugesera Airport
Contract with STEG /Tunisia for construction of 110kV overhead line consisting of all survey studies , foundations , tower erection and stringing and commissioning
Mont Kigali Power Substation, 110 kV/30/15 kV Lines
Contract with ELTEL /Sweden for construction of 110/ 15 kV /50 MVA consisting to all civil works and installation works including all local studies
110 k V /15 k V Ndera Substation including 110 kV transmission line and 15 kV distribution lines
Contract with TAKAOKA /Japan for construction of110 / 15 kV /50 MVA consisting to all civil works and installation works including all local studies...
110 k V/ 30 kV Mukungwa Substation
Contract with CHINT /China for construction of 110 /30 kV /10 MVA transformer bay consisting to all civil works and installation works including related design as well as replacement of.
110 k V/ 30 kV Karongi Substation
Contract with EUCL /Rwanda for rehabilitation of 110/ 30 kV /10 MVA transformer bay consisting to supervision of replacement of the damaged transformer and commissioning of the whole substation