Mont Kigali Power Substation, 110 kV/30/15 kV Lines
The substation was upgraded with two transformers of 20MVA each, replacing the old 10 MVA transformers, which could not cope with the demand during peak hours, sometimes leading to power outages.
The upgrade is part of the Grid Reduction Project, which targets to reduce annual power losses from 19.6 percent, officials said. Government looks to reduce power loses by 1 percent every year.