Contract with STEG /Tunisia for construction of 110kV overhead line consisting of all survey studies ,
foundations , tower erection and stringing and
commissioning
Contract with CHINT /China for construction of 110 /30 kV /10 MVA transformer bay consisting to all civil works and installation works including related design as well as replacement of the overloaded transformer and recommissioning
Construction of a new 110 kV transmission line on lattice towers and ACSR 240/40 conductors with OPGW including all local works , survey , line profile , tower spotting , soil investigation , foundations,
erection of towers, stringing , sagging and stringing.
Commissioning and organization of provisional acceptance
Construction of a new 110 kV transmission line on lattice towers and ACSR 240/40 conductors with OPGW including all local works , survey , line profile , tower spotting , soil investigation , foundations , erection of towers, stringing , sagging and stringing.
Completion tests ,Commissioning and organisation of provisional acceptance.
Construction of a new 110/15 kV Substation starting from the plot arrangement up to commissioning.
Substation Rehabilitation by replacing both High and Medium Voltage equipment including Power
Transformers and indoor Gas Insulated Switchgears
(GIS), Power house and all civil works concerned
The work at Gikondo Substation consisted to Rehabilitation by replacing Outdoor 110kV Switchgears such as Disconnectors, Current and Voltage transformers, Circuit Breakers, Lightning Arrestors, and Bus Bars including all equipment foundations civil works.
Substation Rehabilitation by replacing both High and Medium Voltage equipment including Power
Transformers and indoor Gas Insulated Switchgears
(GIS), Power house and all civil works concerned